While the contract provides for termination in case of a default by a contractor, the Oil Ministry under S Jaipal Reddy in May 2012 had slapped penalty of USD 1.005 billion on RIL for failing to produce natural gas in line with the pre-stated targets.

February 24, 2014 / 16:03 IST
Story continues below Advertisement

With AAP leader Arvind Kejriwal making hike in gas prices a poll issue, Oil Minister M Veerappa Moily has written to Prime Minister Manmohan Singh saying Reliance Industries' contract for KG-D6 gas fields cannot be terminated pending arbitration on issue of output lagging targets.

While the contract provides for termination in case of a default by a contractor, the Oil Ministry under S Jaipal Reddy in May 2012 had slapped penalty of USD 1.005 billion on RIL for failing to produce natural gas in line with the pre-stated targets.

Story continues below Advertisement

Also Read: Oil Ministry seeks legal opinion on RIL bank guarantee

RIL disputed the order and initiated arbitration. "In view of the contractual provision under the PSC, the government will not be able to terminate the contract on account of shortfall in production as the matter is pending before the arbitral tribunal," Moily said in his letter to the Prime Minister.