Green panel defers clearance to NTPC's plant in MP

A high-level committee has deferred a decision on green clearance to NTPC's 2,640 MW power plant in Chhatarpur district of Madhya Pradesh in absence of mandatory firm coal linkage and other stipulations.

June 20, 2015 / 13:52 IST
Story continues below Advertisement

A high-level committee has deferred a decision on green clearance to NTPC's 2,640 MW power plant in Chhatarpur district of Madhya Pradesh in absence of mandatory firm coal linkage and other stipulations.

After detailed deliberations, the Expert Appraisal Committee (EAC) opined that the mandatory firm coal linkage is not available for the project as the environment clearance and forest clearance for the coal block are not available.

Story continues below Advertisement

"As the following information was not available in the EIA/EMP report, and PP could also not provide at the time of presentation, the proposal was deferred," the committee said in its observations.

The company has not proposed 33 percent of the area as green belt and hence, the same needs to be done, it said.