Housing units worth Rs 4.64 lakh crore delayed in 7 top cities despite RERA implementation: ANAROCK

ANAROCK's numbers are higher than real estate data and analytics firm PropEquity's, which recently came out with its report mentioning that 4,65,555 units worth nearly Rs 3.33 lakh crore.


Nearly 5.76 lakh housing units worth Rs 4,64,300 crore are delayed in seven major cities of the country despite implementation of the new real estate law RERA that came into effect May last year, according to property consultant ANAROCK.

Of these delayed housing units that were launched in or before 2013, the ANARCOK report said that Mumbai Metropolitan Region (MMR) and the National Capital Region (NCR) account for 71 percent in volume terms and 78 percent in value terms.

ANAROCK's numbers are higher than real estate data and analytics firm PropEquity's, which recently came out with its report mentioning that 4,65,555 units worth nearly Rs 3.33 lakh crore were behind delivery schedule.

Close

"Incessant project delays, dodgy activities of some developers and land litigation issues have plagued the Indian real estate sector over the last several decades, not helping its domestic and international image," ANAROCK Chairman Anuj Puri said.

He said the government has, over the last few years, taken measures to bring in greater transparency and efficiency in this sector.

"However, despite the implementation of game-changing policies like RERA and GST, the issue of stalled or delayed projects that has primarily been at the core of buyers' discontent is yet to be addressed satisfactorily," Puri rued.

According to the report, the residential real estate launched in or before 2013, that is stuck in various stages of (non) completion, is collectively worth Rs 4,64,300 crore for a total of 5,75,900 units. These units have been stuck since 2013 or before.

MMR and NCR are the two major regions where maximum units with significantly high values have been delayed since their launch in 2013 or before.

As many as 4,10,000 units, worth Rs 3.6 lakh crore, across these two regions are grappling with some deployment issue or the other over the years, resulting in delayed possession. While MMR has 2,10,000 units worth Rs 2,34,000 crore that are stuck, the NCR has 2,00,000 units worth Rs 1,26,000 crore that are pending.

On the other hand, Hyderabad has seen the least project delays during the period, with around 8,900 units worth Rs 5,500 crores delayed since 2013 or before.

In Bengaluru, the delivery of 39,000 flats worth Rs 28,000 crore is delayed, while 10,000 units worth Rs 6,500 crore are yet to be handed over to buyers.

Kolkata has 13,000 units worth Rs 7,300 crore and Pune has 95,000 units worth Rs 57,000 crore that are stuck.

"Major factors contributing to delayed possession of properties across the country include the prolonged liquidity crunch, delayed environmental clearances, land disputes and the non-RERA compliance prevalent across some of the states," Puri said.

The most profound impact of the housing delay is obviously on buyers who have already invested in these projects, affecting their overall financial planning, increasing the burden of rent along with equated monthly installments (EMIs), he added.

Puri noted that the RERA has provisions to ensure timely delivery of projects, but this law has been diluted in many states. For instance, in Karnataka, all projects that are completed by 60 percent or more are currently exempt from RERA purview.

The Great Diwali Discount!
Unlock 75% more savings this festive season. Get Moneycontrol Pro for a year for Rs 289 only.
Coupon code: DIWALI. Offer valid till 10th November, 2019 .
First Published on Aug 27, 2018 01:35 pm
Loading...
Sections
Follow us on
Available On
PCI DSS Compliant
Make every wish come true
10% CashBack on Apparel
10% CashBack on Electronics
Swipe & Win iPhone 11 every hour