Solar energy firms accuse NTPC of delaying issue of CoDs

The National Solar Energy Federation of India has claimed that the power produced from these solar projects is being sold at concessional rates.

July 10, 2017 / 03:49 PM IST
Employees row a boat as they examine solar panel boards at a pond in Lianyungang, Jiangsu Province, China, in this March 16, 2016 file photo. Global funds are cautiously venturing back into Chinese equities after prices collapsed to 4-1/2-year lows in February, taking advantage of cheaper valuations to buy stocks they believe will benefit from China's shift to a consumption-led economy. REUTERS/Stringer/Files    ATTENTION EDITORS - THIS PICTURE WAS PROVIDED BY A THIRD PARTY. THIS PICTURE IS DISTRIBUTED EXACTLY AS RECEIVED BY REUTERS, AS A SERVICE TO CLIENTS. CHINA OUT. NO COMMERCIAL OR EDITORIAL SALES IN CHINA  - RTSCXID

Employees row a boat as they examine solar panel boards at a pond in Lianyungang, Jiangsu Province, China, in this March 16, 2016 file photo. Global funds are cautiously venturing back into Chinese equities after prices collapsed to 4-1/2-year lows in February, taking advantage of cheaper valuations to buy stocks they believe will benefit from China's shift to a consumption-led economy. REUTERS/Stringer/Files ATTENTION EDITORS - THIS PICTURE WAS PROVIDED BY A THIRD PARTY. THIS PICTURE IS DISTRIBUTED EXACTLY AS RECEIVED BY REUTERS, AS A SERVICE TO CLIENTS. CHINA OUT. NO COMMERCIAL OR EDITORIAL SALES IN CHINA - RTSCXID


The National Solar Energy Federation of India (NSEFI) has alleged that state-run power giant NTPC and its trading arm NVVN are delaying issue of commercial operation date (CoD) certificate to solar projects. The CoD is a pre-requisite for selling power at the rate prescribed in the power purchase agreement.

The NSEFI has claimed that the power produced from these solar projects is being sold at concessional rates.

"NTPC and its trading arm NVVN are delaying in providing CoD certificates to plants commissioned in March, 2017, even after three months of their commissioning, although contractually required to provide CoD from 30th day of commissioning," NSEFI said in a letter to power secretary. An NTPC spokesperson did not comment on the matter.

The Ministry of New & Renewable Energy (MNRE) in March 2015 under the National Solar Mission programme came up with a scheme for setting up of 3000 MW (Phase II, Batch II) of Solar power projects under state specific bundling scheme to be implemented through NTPC/NVVN.
Cheap & Clean – How Solar Power May Shape The Future of Modern India

Around 1500 MW of solar power projects have been commissioned in the last three months out of entire 3000 MW awarded under the scheme.

Close

However, the NSEFI said that all these projects are facing significant delays in achieving commercial operation for reasons beyond their control.

This also includes 950 MW projects in Gani-Sakunala Solar Park in Andhra Pradesh.

The NSEFI has told the Power Ministry that it has been over two years since the mandate given to NTPC for implementation of 3000 MW scheme, still MNRE’s nodal agency NTPC has not been able to allocate it's own thermal power for bundling to these projects.

It also said that the NVVN has been citing the delay in approval for allocation of thermal power as a reason for delay in granting CoD approval for these projects.

"Solar power developers are facing significant financial losses, as power is being forcefully billed at concessional rate instead of PPA rate. Developers are left with no option but to get arm-twisted by the NTPC," the NSEFI has said in the letter to the Power Ministry.