Karnataka govt sets 2028 deadline for entire Bengaluru suburban rail project

Benniganahalli- Chikkabanavara suburban rail corridor likely to be ready by 2025

August 11, 2023 / 19:38 IST
Story continues below Advertisement
Bengaluru suburban rail project

The Karnataka government on August 11 set 2028 as the new deadline for completing the long-pending 148-km Bengaluru suburban rail project (four corridors).

While the Union government sanctioned the suburban rail project in October 2020 with a completion time of six years (by 2026), Prime Minister Narendra Modi, who laid the foundation stone in June 2022, stated that the project, first mooted in 1983, would be completed in 40 months.

Story continues below Advertisement

However, Karnataka Infrastructure Development Minister MB Patil, who inspected the Mallige Line of the suburban rail (Benniganahalli- Chikkabanavara) on August 11, said, "This project which runs parallel to the existing South Western Railway (SWR) lines has its challenges but the first corridor (Mallige Line) will be completed in 26 months. So far, 10-15 percent of the work has been achieved related to corridor 2 and ground work will be over in the next 10 months."