Lack of Chinese engineers may hit India power units

Published on Mon, Nov 23, 2009 at 16:43 |  Source : Reuters

Updated at Mon, Nov 23, 2009 at 16:55  

Like this story, share it with millions of investors on M3
0
0
Share on Tumblr
Lack of Chinese engineers may hit India power units

Indian power projects of 4,000 megawatts (MW) capacity may miss their March commissioning date due to a shortage of engineers from Chinese firms that sold the equipment, junior power minister Bharatsinh Solanki said.

India asked all foreign nationals including Chinese engineers to leave the country by October 31, after it found that many with business visas, which are different from work permits, were taking up employment locally.

"The Ministry of Power has requested the Ministry of Home Affairs to expedite issuing of employment visas to the Chinese engineers so that plants can be completed on time," Solanki told lawmakers in a written reply on Monday.

In July, India announced business visas will be issued only to businessmen and that business visa holders employed in India would have to apply for employment visas.

India has issued 38,924 business visas to Chinese nationals until October 2009, while 58,658 visas were issued in calendar 2008.

  

Trending News

Business News

5 ways to use Wolfram Alpha effectively
Subbarao's job just got harder - thanks to Q4 GDP crash "Subbarao's job just got harder - thanks to Q4 GDP crash"

BJP mouthpiece targets Modi, split wide open

China Data Watch China May Official PMI At 50.4 Vs Forecast Of 51.1

The latest earning numbers FIRST on CNBC-TV18
Interviews

May 31 2012, 17:09 | Source: CNBC-TV18

Eyeing 5-6% growth in tractor segment during FY13: M&M  

May 31 2012, 14:55 | Source: CNBC-TV18

Expect reasonable growth in profits ahead: Praj Industries  

Subscribe to

Moneycontrol Newsletters

Moneycontrol.com offers you a choice of various sectoral and other newsletters for FREE!