CAG pulls up BHEL for delays in capacity addition

CAG Audit report examined the adequacy and results of efforts of BHEL from conceptualisation to execution of manufacturing capacity expansion and its utilisation during 2007-12.
  • Language
  • App
  • Subscriptions
  • Specials
  • Sign-In
  • Register
GeStepAhead GrowMyMoney SME Special
moneycontrol.com

Home » News » Business

Feb 18, 2014, 10.13 AM | Source: PTI

CAG pulls up BHEL for delays in capacity addition

CAG Audit report examined the adequacy and results of efforts of BHEL from conceptualisation to execution of manufacturing capacity expansion and its utilisation during 2007-12.

Like this story, share it with millions of investors on M3

CAG pulls up BHEL for delays in capacity addition

CAG Audit report examined the adequacy and results of efforts of BHEL from conceptualisation to execution of manufacturing capacity expansion and its utilisation during 2007-12.

Post Your Comments

Share Cancel

Government auditor CAG today pulled up state-owned  BHEL for delays in augmenting the equipment manufacturing capacity, needed for supporting the expansion of power sector.

"While CEA (Central Electricity Authority) identified power generation capacity addition requirements of 67,439 MW for XIth plan period (2007-12) in the country in November 2003 itself, BHEL completed the first phase of its capacity addition programme in March 2011," Comptroller and Auditor General of India said in its report tabled in Parliament.

Thus, the manufacturing capacity expansion, which was required to be planned and completed in the initial years of the XIth plan was declared to have been completed by BHEL only towards the end of the plan, it said.

"Implementation of the capacity expansion programmes for the XI and XIIth Plans disclosed delays between seven months and 62 months in 17 selected schemes out of 22 schemes approved in 2007-12," CAG said in the report.

Also Read: Par Panel seeks review of OVL's Imperial Energy acquisition

In addition to some uncontrollable factors, it said, delays due to reasons like non-fixation of targets for vendors to erect and commission machines, replacement of damaged equipment and delays in pre-ordering activities could have been minimised through improvements in market research, planning and monitoring.

"Existing installed manufacturing capacity for turbines, generators and boilers during 2007-11 remained largely under utilised," the report added.

There was considerable scope for improved utilisation. Though capacity utilisation picked up during 2011-12, there is a need to maintain and further improve it in order to achieve the benefits of ongoing capacity augmentation.

Further, audit observed delay in delivery of equipments ranging between 7 and 68 months in 126 out of 151 sets delivered by BHEL to its customers during 2007-12.

CAG Audit report examined the adequacy and results of efforts of BHEL from conceptualisation to execution of manufacturing capacity expansion and its utilisation during 2007-12. 

The CAG report said: "Apart from the need for better preparedness, capacity augmentation in different segment was also required to match plan requirements.

"Against the projected requirements of 8,200 MW and 31,860 MW for the country in supercritical (energy efficient) thermal segment during XI and XII plans, the capacity augmentation planned by BHEL was only 5,280 MW and 18,000 MW respectively."

CAG also recommended that the Ministry of Heavy Industries and Public Enterprises consider reviewing performance parameters and fix challenging targets in MoU to provide a more realistic and objective basis for assessment of performance of BHEL.

It said that BHEL may review the pricing mechanism of its equipment to make it more competitive by adopting appropriate costs including employee costs.

BHEL may work out a time bound programme for increasing outlays on R&D (research and development) activities, particularly in core areas so as to convert these into advantages in competition, it said.

CAG added that the monitoring mechanism in BHEL may be strengthened to minimise controllable delays in project execution and delivery by fixing periodicity and levels of monitoring up to the Board of Directors.

Ads by Google

Buy, Hold, Sell ? Hear it first on M3
CAG pulls up BHEL for delays in capacity addition

See all

Get started using your favorite social network

or

Login using moneycontrol ID

Username
Password

Need help logging in? Reset password.

Don´t have an account? Sign Up

Get started using your favorite social network

or

Simply sign up using this short form

* mandatory

UserName*

Username should be atleast 4 character

Password*

Password should be 8 or more characters,
atleast 1 number, 1 symbol & 1 upper case letter

Alert

Your Password should contain
  • 8 or more characters
  • At least 1 number
  • At least 1 symbol
  • At least 1 upper case letter
Confirm Password*
Email
Already have an account? Login