The company has submitted development plans for D6 satellite fields. "We estimate D6 Phase-I initial field development costs at USD 5.2 billion. 14 of the 18 planned Phase-I wells will be tied in after the start-up. D6 development provides flexibility to up production to 4.2 bcf/d." It has also submitted development plans for eight national gas discoveries in D6. "The initial field development costs for MA oil discovery stands at USD 1.5 billion. A large portion of the Block MA development cost is to tie in 4 of the 6 planned oil wells." Reliance Industries-Niko plans to convert some oil wells after the gas production period. RIL said it has completed initial drilling in NEC-25. "Results are under evaluation.” The company plans to submit development plans for six gas discoveries declared commercial. It will select initial drilling location in D4 block as early as mid-CY09. The oil major holds 90% in D6 block, while Niko Resources holds 10% stake. |
|
|
|