NSE Announcements on Era Infra Eng
Posted by :
MMB MessengerEra Infra Engineering Limited has informed the Exchange that "Era Infra Engineering Limited an integrated development company with a pan India presence has secured contracts worth Rs 1,26,33,34,441/-for: (1) The work for Piling and Foundations works at Anpara-D Thermal Power Plant (PTPP) of UPRUVNL at Anpara, Sonebhadra, U.P. by Bharat Heavy Electricals Limited (BHEL) valuing Rs 77,42,00,000/- and (2) Construction of various Building at BHU Varanasi, Package-I consisting of 14 Buildings by Central Public Works Department (CPWD) valuing Rs 48,91,34,441/-....
BSE Announcements on Era Infra Eng
Posted by :
MMB Messenger
Era Infra Engineering Ltd has informed BSE that the Company has secured contracts worth Rs. 1,26,33,34,441/- for:
1. The work for Piling and Foundations works at Anpara-D Thermal Power Plant (PTPP) of UPRUVNL at Anpara, Sonebhadra, U.P. by Bharat Heavy Electricals Ltd. (BHEL) valuing Rs. 77,42,00,000/- and
2. Construction of Various Building at BHU Varanasi, Package-I consisting of 14 Buildings by Central Public Works Department (CPWD) valuing Rs. 48,91,34,441/-....
Era Infra Order Book SWELLING
Posted by :
zraja
Era Infra bags Contracts of Rs. 1,26,33,34,441/-
Announcement: Era Infra Engineering Ltd has informed BSE that the Company has secured contracts worth Rs. 1,26,33,34,441/- for:
1. The work for Piling and Foundations works at Anpara-D Thermal Power Plant (PTPP) of UPRUVNL at Anpara, Sonebhadra, U.P. by Bharat Heavy Electricals Ltd. (BHEL) valuing Rs. 77,42,00,000/- and
2. Construction of Various Building at BHU Varanasi, Package-I consisting of 14 Buildings by Central Public Works Department (CPWD) valuing Rs. 48,91,34,441/-.
ZRAJA...
NSE Announcements on Era Infra Eng
Posted by :
MMB MessengerEra Infra Engineering Limited has informed the Exchange that: "Era Infra Engineering limited an integrated development company with a pan India presence has secured contracts worth Rs 1,26,33,34,441/- for: 1) The work for Piling and Foundations works at Anpara-D Thermal Power Plant (PTPP) of UPRUVNL at Anpara, Sonebhadra, U.P. by Bharat Heavy Electricals Limited (BHEL) valuing Rs 77,42,00,000/- and 2) Construction of Various Building at BHU Varanasi, Package-I consisting of 14 Buildings by Central Public Works Department (CPWD) valuing Rs 48,91,34,441/-"....
NSE Announcements on Era Infra Eng
Posted by :
MMB MessengerEra Infra Engineering Limited has informed the Exchange that pursuant to the allotment of 2,10,00,000 convertible warrants on October 10, 2009, the company has recieved full consideration, alongwith the request, for exercise of conversion option by the holders of remaining 1,40,00,000 convertible warrants. Consequently, the Share Allotment Committee of the Board of Directors of the Company at their meeting held on October 24, 2009 has allotted 1,40,00,000 equity shares of Rs.2/- each issued at a premium of Rs.83/- per share. The details of the same shall be available on the NSE website (http://www.nseindia.com) under: Corporates > Latest Announcements and on the Extranet Server (/Common/Corporate Announcements). ...
BSE Announcements on Era Infra Eng
Posted by :
MMB Messenger
Pursuant to the allotment of 2,10,00,000 convertible warrants on October 10, 2009, Era Infra Engineering Ltd has informed BSE that now the Company has received full consideration, along with the request, for exercise of conversion option by the holders of remaining 1,40,00,000 convertible warrants.
Consequently the Share Allotment committee of the Board of Directors of the Company at their meeting held on October 24, 2009 has allotted 1,40,00,000 equity shares of Rs. 2/- each issued at a premium of Rs. 83/- per share. ...
Era Infra Results on 31 Oct 2009
Posted by :
zrajaThe Q2 results are on 31 Oct 2009, the scrip seems to be touching new heights in the near future, even the promoter group is converting their warrants into equity shares, considering the valuations and the order book position, one can remain invested for long and can obtain decent returns in the near future, ZRaja....
Allotment of shares upon the conversion of warrants
Posted by :
vkk43
Pursuant to the allotment of 2,10,00,000 convertible warrants on October 10, 2009, Era Infra Engineering Ltd has informed BSE that now the Company has received full consideration, along with the request, for exercise of conversion option by the holders of remaining 1,40,00,000 convertible warrants.
Consequently the Share Allotment committee of the Board of Directors of the Company at their meeting held on October 24, 2009 has allotted 1,40,00,000 equity shares of Rs. 2/- each issued at a premium of Rs. 83/- per share. ...
hold it upto 232.00
Posted by :
Guesthold it.it will come upto next friday....accumulate......
buy
Posted by :
stocktobuyi recommend buy on Era Infra Eng.buy on dips and accumlate...
Era Inra - Sunidhi Securities Target
Posted by :
zrajaEra Infra seems to be touching Sunidhi Securities target of 210, given the order book position, its execution period, and valuations it appears to be a good stock to hold on to it. Moreover, the Q2 results around the corner, one can expect decent returns, Thanks, ZRaja....
era infra
Posted by :
goldentipEra is doing extremely well and valuation wise it is way cheaper than other construction majors. The way business is shaping up for Era, if it is able to maintain its margins and if there is no major concern on the interest front (we`ll need to watch out for Q2 results) there is a case for rerating. ...