MARKET RADAR
SENSEX     NIFTY      Refresh
Sadbhav Engineering Directors Report, Sadbhav Eng Reports by Directors
YOU ARE HERE > MONEYCONTROL > MARKETS > CONSTRUCTION & CONTRACTING - CIVIL > DIRECTORS REPORT - Sadbhav Engineering
Sadbhav Engineering
BSE: 532710|NSE: SADBHAV|ISIN: INE226H01026|SECTOR: Construction & Contracting - Civil
SET ALERT
|
ADD TO PORTFOLIO
|
WATCHLIST
LIVE
BSE
May 25, 17:00
123.75
2.15 (1.77%)
VOLUME 2,339
LIVE
NSE
May 25, 17:00
123.45
2.5 (2.07%)
VOLUME 66,133
« Mar 10
Directors Report Year End : Mar '11
The Members,
 
 The Directors have the pleasure in presenting the Twenty Second Annual
 Report together with the audited statement of accounts for the year
 ended March 31, 2011.
 
 Financial Results                                 (Rs. in crores)
 
                                           Current Year  Previous Year
 
                                              2010-2011      2009-2010
 
 Income from Operations                         2209.17        1256.93
 
 Profit before Interest, Depreciation & Tax      245.30         154.31
 
 Less : Interest & Finance Charges                42.69          33.09
 
 Depreciation                                     26.86          23.25
 
 Profit before Tax                               175.75          97.97
 
 Less : Provision for tax                         57.56          29.70
 
 Provision for deferred tax liability/(asset)      1.99           3.08
 
 Profit after Tax                                116.20          65.19
 
 Add : Excess (Short) provision for taxation 
 of earlier years                                  3.39         (11.35)
 
 Net Profit for the year                         119.59          53.84
 
 Balance brought forward from last year          172.56         137.05
 
 Amount available for Appropriations             292.15         190.89
 
 Appropriations
 
 Transfer to General Reserve                      12.00           6.50
 
 Transfer to Debenture Redemption Reserve          6.00           6.00
 
 Proposed Dividend                                 8.99           5.00
 
 Tax on Proposed Dividend                          1.49           0.83
 
 Balance carried to Balance Sheet                263.66         172.56
 
 Dividend
 
 The Directors are pleased to recommend for approval of the shareholders
 dividend of 60% (Rs. 0.60 per equity share of Re 1 each) for the
 financial year ended March 31, 2011. The final dividend, if approved,
 will absorb a sum of Rs. 8.99 Crores and dividend tax of Rs 1.49
 Crores.
 
 Business Overview
 
 The total income from operations during the year under review was Rs.
 2209.17 Crores against Rs. 1256.93 Crores for the previous year
 recording the growth of 75.76% . Operating Profit (PBDIT) for the
 current year is Rs.245.30 Crores (Rs.154.31 Crores in previous year)
 thereby recording the growth of 58.96 %. Net Profit after tax is
 amounted to Rs.119.59 Crores (Rs 53.84 Crores in previous year )
 thereby recording a growth of 122.12 %.
 
 Operations
 
 Ongoing Works
 
 The following major works are under execution and the same are
 progressing satisfactorily.  
 
                                                   (Rs. in crores)
 
 Sector           No. of 
                projects     Work order     Work done     Work on hand
 
 Roads & Highways    13         7505.31       2871.18        4634.13
 
 Irrigation          12         1457.10        324.63        1132.47
 
 Mining Operation     9         1527.61        707.46         820.15
 
 Total               34        10490.02       3903.27        6586.75
 
 The Company''s order book (pending execution) shows work on hand
 amounting to Rs. 6586.75 Crores as on the June 30, 2011.
 
 New contracts / projects
 
 Your Company has been awarded following new contracts/projects during
 the year and up to the date of this report.
 
 Road Sector
 
 1.  Improvement/Upgradation Strengthening/Widening of
 Govindpur-Sahibganj State Road Project (Govindpur-Jamtara Contract
 Package No. I) by Road construction Department, Govt. of Jharkhand for
 contract price of Rs. 229.91 crores in joint venture with GKC Projects
 Ltd.-Hyderabad. Company is leading the joint venture with 50%
 participation share i.e. for Rs. 114.95 cores.
 
 2.  Rehabilitation and Up-gradation to 2-lane with paved shoulders and
 maintenance of Multai-Chhindwara-Seoni Section of NH-69A and
 Narsinghpur-Amarwara-Saoner Section of NH-26B in Madhya Pradesh and
 Maharashtra including construction and maintenance of Ring Road and
 connecting roads in Chhindwara Town by NHAI for price of Rs. 1411.36
 cores.
 
 Irrigation Sector
 
 1.  Execution of Omkareshwar Right Bank Lift Canal including its
 distribution network up 40 Ha. Chak for culturable command areas (CCA)
 of about 29947 Ha. on Turn Keybasis from RD 51.281 to 125. Km
 (excluding V.R.B. at RD 51.281 Km Wasvi-Sirsodia Road) by Narmada
 Development Division 20, M.P. for contract value of Rs.349.30 crores in
 joint venture with GKC Projects Limited Hyderabad. Company is leading
 the joint venture with 60% participation share.
 
 2.  Execution of Omkareshwar Right Bank Lift Canal including its
 distribution network up 40 Ha. Chak for culturable command areas (CCA)
 of about 28073 Ha. on Turn Keybasis from RD 0.00 Km to 51.281. Km
 (including V.R.B. at RD 51.281 Km Wasvi- Sirsodia Road) by Narmada
 Development Division 20, M.P. for contract value of Rs. 519.93 crores
 in joint venture with GKC Projects Limited Hyderabad. Company is
 leading the joint venture with 40% participation share.
 
 3.  Work of EPC contract for construction of Radhanpur Sub Branch
 Canal, Manpura Sub Branch Canal, Distributaries & Minors of Radhanpur
 Branch Canal, RSBC & MSBC (Earthwork, lining, Structures, Service Road,
 CR/Escape/HR, Gates, Stop logs, Control Cabin) including Geo Tech
 investigation, Design of structures and Operation and maintenance for
 the same for five (5) years for contract price of Rs. 236.20 crores in
 joint venture with GKC Projects Limited Hyderabad. Company will lead
 the joint venture with 52% participation share.
 
 Mining Sector
 
 1. Blast hole drilling, controlled blasting with shock tube initiation
 (Nonels), excavation, loading, transportation, dumping, spreading and
 leveling etc., of 436.50 LBCM over burden, at Manugur OC-II Extension
 (Phase-II) Project by The Singareni Collieries Company Limited for
 contract amount of Rs. 182.50 crores in joint venture with GKC Projects
 Limited – Hyderabad.  Company is leading the joint venture with 51%
 participation share i.e. for Rs. 93.07 crores of which work amounting
 to Rs. 26.01 crores has been completed.
 
 Transfer of BOT Projects
 
 Company has entered into Agreement with M/s Norwest Venture Partners
 (NVP)& The Xander Group Inc (Investors) wherein over a period of time,
 subject to necessary approvals, consents to the extend required from
 various authorities shares held by Company in nine of the subsidiaries/
 joint venture companies have been/ would be transferred to Sadbhav
 Infrastructure Project Limited (SIPL) a subsidiary of Company.
 Investors have invested a sum of Rs. 400.00 croes for acquiring 22.22%
 stake on fully diluted basis in SIPL. This re-structuring and fund
 raising would help Company to leverage its finance more effectively and
 raising funds for the new project would now be done through SIPL.
 Company now holds around 83% equity in SIPL and accounts of SIPL along
 with subsidiaries/ joint venture companies have been consolidated with
 the financials of Company. Brief summary of each of the Project is as
 under :
 
 Name of the        Details of Project                    Cost of the
 Company                                                   Project
                                                           (Rs. in 
                                                            Crores)
 
 Mumbai-Nasik       Vadape-Gonde 4 Lane BOT project          794.58
 Expressway Limited for widening the existing two-lane
 (MNEL)             of 99.50 Kms to four lanes and its
                    operation and maintenance.
 
 Ahmedabad Ring     4-laning the present 76.21 km two-       500.80
 Road 
 Infrastructure     lane ring road around Ahmedabad
 Ltd. (ARRIL)       city and its operation & maintenance
 
 Aurangabad-Jalna   Widening the existing two-lane           277.00
 
 Tollway Ltd.       stretch of 65.80 kms to four lanes
 
 (AJTL)             and its operation and maintenance
 
 Nagpur Seoni       - Rehabilitation and upgrading to        489.70
 
 Expressway Ltd.    four lane from km. 596/750 to km.
 
 (NSEL)             653/225 on NH-7 in the state of
 
                    Madhya Pradesh under North-
 
                    South Corridor (NHDP Phase II)
 
                    on BOT-Annuity basis.
 
                    - The project is a 51:49 joint
 
                    venture between the Company & its
 
                    associates and SREI Infrastructure
 
                    Finance Limited.
 
 Dhule Palesner     - Design, Engineering, Finance,         1420.00
 
 Tollway Ltd.       Procurement, Construction,
 
 (DPTL)             Operation and Maintenance of 4/6
 
                    laning of MP/ Maharashtra Border-
 
                    Dhule section of NH- 3 from km
 
                    168.500 to km 265.000 in the
 
                    State of Maharashtra under NHDP
 
                    Phase IIIA on BOT (Toll) Basis
 
                    - The project is in joint venture
 
                    between the Hindustan
 
                    Construction Company Ltd., John
 
                    Laing Investment Ltd and Company
 
                    & its associates in a ratio of
 
                    37:36:27 respectively
 
 Maharashtra Border - Modernization and computerization    1426.37
 
 Check Post Network of integrated border check posts
 
 Ltd. (MBCPL)       at 22(Twenty Two) locations in
 
                    the State of Maharashtra on Build
 
                    Operate and Transfer (BOT) Basis.
 
                    - The project is in joint venture
 
                    between Company & its associates,,
 
                    SREI Infrastructure Finance Limited
 
                    and SREI Sahaj e-village Limited in
 
                    ratio of 90:05:05 respectively
 
 Hyderabad-Yadgiri  - Design, Engineering, Construction,    480.22
 
 Tollway Pvt. Ltd.  Development, Finance, Operation
 
                    and Maintenance of four laning of
 
                    Hyderabad- Yadgiri Section from
 
                    km 18.600 to km 54.000 of NH-202
 
                    in the state of Andhra Pradesh
 
                    under NHDP Phase-III on DBFOT
 
                   (Toll) Basis Package No. NHDP-III/
 
                    BOT/AP/04.
 
                    - Equity component of the project
 
                    shared by Sadbhav Infrastructure
 
                    Project Ltd., and GKC Projects Ltd
 
                    in ratio of 60:40 respectively
 
 Rohtak-Panipat     Four laning of Rohtak to Panipat       1213.40
 
 Tollway Pvt. Ltd.  Section of NH-71A from km 0.000
 
                    Km 63.30 of NH-10 to km 80.858
 
                    Km 83.50 of NH-1 in the state of
 
                    Haryana on BOT basis under NHDP
 
                    Phase-III
 
 Bijapur-Hungund    - Project consists of four laning of   1257.10
 
 Tollway Pvt. Ltd.  Bijapur – Hungund Section of
 
                    NH-13 from km 102.000 to km
 
                    202.000 in the state of Karnataka
 
                    on Design, Build, Finance, Operate
 
                    and Transfer (DBFOT), Toll basis
 
                    under NHDP Phase-III Package No.
 
                    NHDP-III/BOT/KNT/05
 
                    - Equity component of the project
 
                    shared by Sadbhav Infrastructure
 
                    Project Ltd., and Monte Carlo
 
                    Construction Ltd. in ratio of 77:23
 
                    respectively.
 
 Name of the
 Company              Status          Toll Revenue    % Shareholding
                      as on           of the
                                                       SEL       SIPL
                      30/06/2011      F.Y. 2010-11
                                      (Rs. in
                                      Crores)
 
 Mumbai-Nasik
 Expressway Limited
 (MNEL)               Completed        51.26            20         -
                      (except one
                      ROB for
                      which Work
                      In Progress)
 
 Ahmedabad Ring
 Road Infrastructure
 Ltd. (ARRIL)         Completed        63.42             -        80 
 
 Aurangabad-Jalna
 Tollway Ltd.
 (AJTL)               Completed        23.69             -        51
                     (except ROB
                      for which
                      Work In
                      Progress)
 
 Nagpur Seoni
 Expressway Ltd.
 (NSEL)               Expenditure          -            51         -
                      to the
                      extent of Rs.
                      292.89 Crore
                      has been
                      incurred.
                      Project
                      is under
                      suspension
                      and matter is
                      subjudice.
 
 Dhule Palesner
 Tollway Ltd.
 (DPTL)               949.00               -            27         -
                     (as on 15th
                      July 2011)
 
 Maharashtra Border
 Check Post Network
 Ltd. (MBCPL)         475.39               -            63        27
 
 Hyderabad-Yadgiri
 Tollway Pvt. Ltd.    232.99               -             -        60
 
 Rohtak-Panipat
 Tollway Pvt. Ltd.    149.12               -             -       100
 
 Bijapur-Hungund
 Tollway Pvt. Ltd.    790.06               -             -        77
 
 
 Joint Ventures
 
 The Company has the following joint ventures –
 
 SEL- GKC Joint Venture :
 
 Over and above the Road, Irrigation and Mining Projects as mentioned
 above, Company is executing following projects in Joint Venture with
 GKC Project Ltd.
 
 1.  Earth work excavation, forming embankment and construction of CD &
 CM works of main canal and distributory system upto water course level
 and CC lining to main canal and other allied works including
 investigation, designing and estimation of Gouravelly right side canal
 from km 0.000 to 47.725 and left side canal in Karimnagar District. The
 cost of the project is Rs. 166.88 croes of which company''s share is 52
 % i.e. Rs.86.78 crores of which work amounting to Rs.36.93 crores has
 been completed.
 
 2.  Investigation, design and execution of Canal Network System
 including Earth work Excavation and Forming Embankment, Construction of
 CM & CD Works and lining of canals up to sub minors and formation of
 Field Channels including Structures to serve an ayacut of 58800 Acres
 in Karimnagar Dist under Kodlmial, Potharam Surampet Lachupet and New
 tanks at  450 and its Concerned Gravity Canals ( Canal Network Package
 III). The cost of project is Rs. 99.31 crores of which company''s share
 is 52% i.e Rs. 51.64 crores of which work amounting to Rs. 16.33 crores
 has been completed.
 
 3.  Investigation, Survey, Design and Construction of Bus Rapid Transit
 System (BRTS) corridor from Pendurthi to DRM Office (PTC Corridor) via
 NAD Jn, Kancharapalem, Railway Station with 2 years defect liability
 period under EPC(Design & Build) system.  The cost of project is Rs.
 165.54 crores of which company''s share is 50% i.e. Rs. 82.77 crores of
 which work amounting to Rs. 47.46 crores has been completed.
 
 Sub Division of Equity Shares :
 
 Pursuant to the approval of Shareholders through the process of Postal
 Ballot nominal value of Equity Share of Rs. 10/- has been sub-divided
 in to 10 Equity Shares of Re 1/- each.
 
 Right Issue :
 
 Through letter of offer dated August 04,2010 Company made Right Issue
 of 6,25,000 equity shares of Rs. 10 each for cash at premium of Rs. 715
 per equity share aggregating Rs. 45.31 crores . As per terms of offer,
 allottees in Right Issue were also allotted 3 Detachable Warrants for
 every one equity share. Right Issue which opened for subscription on
 August 18,2010 closed on September 6, 2010 was oversubscribed.
 Allotment of 6,25,000 equity shares were made on September 16,2010.
 
 The details of utilization of fund v/s projection made in Letter of
 offer dated August 04, 2010 are as under : 
 
                                                     (Rs. in crores)
 
 Particulars                              Proposed  Utilized 
                                                       up to  Balance
                                       Utilization    31/03/
                                                        2011    Funds
 
 Investment in projects directly or 
 through Subsidiaries/Joint Ventures/Spvs   18.48      18.48    0.00
 
 Margin Money/ investment for 
 purchase of Capital Equipment              16.45       4.27   12.18
 
 General Corporate Purposes                  8.66       8.66    0.00
 
 Issue Expenses                              1.72       1.44    0.28
 
 Total                                      45.31      32.85   12.46
 
 As per the terms of offer document, untilised balance fund has been
 utilized towards working capital requirement.
 
 Allotment of Detachable Warrants :
 
 As per the terms of Right Issue, Company has issued and allotted
 18,75,000 the Detachable Warrants convertible in to equal number of
 Equity Shares of Rs. 10/- each on September 16,2010, which were due for
 conversion into Equity Shares between December 16,2010 to March 15,2012
 (Warrant Exercise Period) at an exercise price of Rs. 425/-. The said
 Detachable Warrants were subsequently adjusted to 1,87,50,000
 Detachable Warrants convertible in to equal number of Equity Shares of
 Re 1/- each at price of Rs. 42.50/- per share on account of split of
 the face value of Equity Share from Rs. 10 each to Re 1/- per share.
 
 Thereafter as per letter of offer, on December 18, 2010, Board of
 Directors exercised Call Option for compulsory conversion of Detachable
 Warrants into Equity Shares.
 
 The details of the allotment made on exercise of conversion of the
 Detachable Warrants by warrant holders are as under :
 
 Particulars                              No. of Equity 
                                        Shares Allotted      Date of
                                                           Allotment
 
 Voluntary Conversion- First Tranche            1278120     5/1/2011
 
 Voluntary Conversion- Second Tranche           2524490   19/01/2011
 
 Compulsory Conversion- Exercise of 
 Call Option                                   14823190   24/02/2011
 
 Total                                         18625800
 
 No of Warrants lapsed since not applied 
 for conversion                                  124200
 
 Total                                         18750000
 
 Company received Rs. 79.16 crores towards subscription of Detachable
 Warrants.
 
 Employee Stock Option Scheme :
 
 The Company implemented the ''Sadbhav Employee Stock Option Scheme 2008
 (ESOS Scheme 2008) pursuant to the resolution passed by the members at
 the 19th Annual General Meeting held on September 27, 2008. The
 Remuneration Committee of Board at its meeting held on October 04, 2010
 granted 2,50,000 Employee Stock Options exercisable into 2,50,000
 Equity Shares of Rs. 10 each, to eligible employees at a price of
 Rs.500/- per share. The said 2,50,000 Employee Stock Options were
 subsequently sub-divided in to 25,00,000 to match the reduced nominal
 value of Re 1. Remuneration Committee administers and monitors the
 Scheme.
 
 The applicable disclosures as stipulated under SEBI (Employee Stock
 Option Scheme & Employee Stock Purchase Scheme) Guidelines, 1999, is
 provided in Annexure-I forming part of this report.
 
 Company has received certificate from Auditors of Company confrming that
 scheme has been implemented in accordance with SEBI Guidelines and
 resolution passed by Shareholders. Auditors certificate would be placed
 at Annual General Meeting for inspection by members.
 
 Search and Seizure Operation under Income Tax Act :
 
 During the period under review search and seizure operation under
 section 132 of the Income Tax Act, 1961 had taken place in the premises
 of the Company and its Directors. During the course of search no
 seizure was made by the Income tax department and the Company has not
 disclosed any undisclosed income. No demand notice of income tax has
 been served on Company till date pursuant to the said search.
 
 Subsidiary Company
 
 Pursuant to the General Exemption granted by Central Government vide
 General Circular No. 2/2011 dated February 08, 2011 and the resolution
 passed by the Board of Directors on April 20, 2011, copies of Balance
 Sheet, Profit and Loss Account, Report of Board of Directors and the
 Report of the Auditors of subsidiary companies have not been attached
 with the Annual Accounts of the Company under Section 212 of Companies
 Act 1956. As required under the circular statement giving required
 details is enclosed with the consolidated balance sheet. The Company
 will keep these documents at the Registered Office of the Company and
 its subsidiaries and make them available upon the request by any
 shareholder of Company.
 
 Consolidation of Accounts
 
 Further pursuant to the Accounting Standard AS-21 issued by the
 Institute of Chartered Accountants of India, Consolidated Financial
 Statement presented by the Company includes the financial statement of
 its subsidiaries which have commenced activities.
 
 Fixed Deposit
 
 The company has not accepted any deposits as defined under Section 58A
 of the Companies Act, 1956 read with the Companies (Acceptance of
 Deposits) Rules, 1975, as amended, during the year under review.
 
 Directors
 
 Shri Atul N. Ruparel and Shri Sandip V. Patel are the directors liable
 to retire by rotation at the ensuing Annual General Meeting and, being
 eligible, offer themselves for reappointment.
 
 Directors'' Responsibility Statement
 
 Pursuant to the requirement under Section 217(2AA) of the Companies
 Act, 1956, with respect to Directors'' Responsibility
 
 Statement, it is hereby confrmed that –
 
 (i) in the preparation of the annual accounts, accounting standards
 have been followed along with proper explanation relating to material
 departure;
 
 (ii) such accounting policies have been selected and applied
 consistently and have made judgments and estimates reasonable and
 prudent so as to give a true and fair view of the state of affairs of
 the Company at March 31, 2011 and the Profit of the Company for the
 year ended on that date;
 
 (iii) proper and sufficient care has been taken for the maintenance of
 adequate accounting records in accordance with the provisions of the
 Companies Act, 1956 for safeguarding the assets of the Company and for
 preventing and detecting fraud and other irregularities; and
 
 (iv) the accounts have been prepared on a ''going concern'' basis.
 
 Auditors :
 
 M/s. Shashikant Patel Associates, Chartered Accountants, the Statutory
 Auditors, retire at the ensuing Annual General Meeting and are eligible
 for re-appointment. Your Directors have recommended the re-appointment
 of M/s. Shashikant Patel Associates, Chartered Accountants as Auditor
 of the Company. The Auditor''s have confrmed that their appointment, if
 made, would be within limit prescribed under Section 224(1B) of the
 Companies Act, 1956 and they are not disqualified, within the meaning of
 Sub- sections (3) and (4) of Section 226 of the Companies Act, 1956.
 
 Auditors'' Report :
 
 The Auditors'' have not made any adverse comments / remarks which
 requires clarification from the Directors of Company and accordingly no
 further explanation has been provided by the directors in term of
 section 217 of the Companies Act, 1956.
 
 Corporate Governance
 
 The Company has been proactive in following the principles and
 practices of good corporate governance. The Company has ensured that
 the Corporate Governance requirements as stipulated in Clause 49 of the
 Listing Agreement with the Stock Exchanges are duly complied with. A
 report on Corporate Governance along with a certificate from the
 Auditors regarding compliance of Clause 49 of Listing Agreement is
 annexed.
 
 Industrial Relations
 
 The Company enjoyed cordial relations with the employees during the
 year under review and the Management appreciates the employees of all
 cadres for their dedicated services to the Company.
 
 Particulars of Employees
 
 Information as per Section 217(2A) of the Companies Act, 1956 read with
 the Companies (Particulars of Employees) Rules, 1975 as amended, is
 given in the Annexure-II and forms part of this Report.
 
 Energy Conservation, Technology Absorption and Foreign Exchange Earning
 and Outgo
 
 The rules regarding conservation of Energy and Technology Absorption
 are not applicable to the Company. The particulars of the expenditure
 in Foreign Currency and earning in Foreign Exchange are given in Notes
 to Accounts (Schedule 23).
 
 Acknowledgements
 
 The Directors wish to express their appreciation for the support and
 co-operation of the Central and State Government, Bankers, Financial
 Institutions, Suppliers, Vendors, Associates, Subcontractors and
 Shareholders during the year under review. Your Directors wish to place
 on record their appreciation for the employees of the Company at all
 levels for their commitment, dedication and continued support to the
 Company.
 
                          For and on behalf of the Board of Directors
 
 Place : Ahmedabad                                Vishnubhai M. Patel
 
 Date : July 30, 2011                                        Chairman
 
 
 
 
 
 
 
 
 
 
 
Source : Dion Global Solutions Limited
Quick Links for sadbhavengineering
Explore Moneycontrol
Stocks     A | B | C | D | E | F | G | H | I | J | K | L | M | N | O | P | Q | R | S | T | U | V | W | X | Y | Z | Others
Mutual Funds     A | B | C | D | E | F | G | H | I | J | K | L | M | N | O | P | Q | R | S | T | U | V | W | X | Y | Z
Copyright © e-Eighteen.com Ltd. All rights reserved. Reproduction of news articles, photos, videos or any other content in whole or in part in any form or medium without express written permission of moneycontrol.com is prohibited.